Aller au contenu
Étude de cas

Nordic steelmaker — 300 MW baseload hydro + offshore

Capacité
300 MW
Durée
20 ans
Techno
Hydro + offshore wind
Pays
Suède / Allemagne

Acheteur : Sidérurgiste européen top 10 · Vendeur : Utility nordique + offshore developer · Date : 2026-02-04

For CBAM 2026 compliance and low-carbon steel labelling, the steelmaker structured a hybrid PPA: 180 MW Swedish hydro (SE3) baseload + 120 MW German offshore (DE) pay-as-produced. Voltarione coordinated DD and credit scoring in 9 weeks.